CLIENTS BENEFITS

Attention Property Managers

 

CCF Can Save You 15% On Your Next Repair Or Build Out!!

 

 

If you employ a General Contractor to carry out repairs or new tenant build outs on your properties CCF can save you the GC Profit margin by simply procuring qualified sub-contractors and carrying out all Project Management duties.

 

Typically these are “overhead” costs billed by any reputable GC and then a 10 to 15% markup is added to the final cost.

 

Typical Example. Lets consider a small office Build-out for a new Tenant involving:

 

 


GENERAL CONTRACTOR

TRADE                                       SUBS PRICE

Demolition                                         $1,275.00

Framing                                             $   875.00

Drywall                                               $1,460.00

Painting                                             $   935.00

Acoustical Ceiling                            $   580.00

Trim Carpentry                                  $1,100.00

Flooring                                             $2,500.00

                        SUB TOTAL              $8,725.00

 

10% Overhead                                  $   872.50

15% Profit                                          $1,439.62

 

            FINAL TOTAL                      $11,037.12

 

 

CCF CONSTRUCTION SERVICES

TRADE                                       SUBS PRICE

Demolition                                         $1,275.00

Framing                                             $   875.00

Drywall                                               $1,460.00

Painting                                              $   935.00

Acoustical Ceiling                             $   580.00

Trim Carpentry                                  $1,100.00

Flooring                                             $2,500.00

                        SUB TOTAL              $8,725.00

 

Bid Procurement                              $   420.00

6% Project Management Fee        $   523.50

 

            FINAL TOTAL                      $9,668.50